On site now:Concrete sub-base, Box tree installation, Irrigation laterals, heads and drip

45%

complete

Week 9 of 20
Updated Oct 30

On site this week

Starting in the next two weeks

Needed from you

  • Stone setter scheduled behind the concrete sub-baseOct 12 to Nov 20

Next payment

Progress payment 4

Oct 30 (end of week 8)

Due

Latest updates

Every Friday

  1. Oct 30 · Week 8

    Progress payment 4 issued

    Rough masonry and specimen trees are complete. Concrete sub-base and box trees are under way.

  2. Oct 23 · Week 7

    Rough masonry complete

    Fire pit, BBQ, approach walls and planter walls are up and ready for finishes.

  3. Oct 9 · Week 5

    Specimen trees set

    Eight Medjool date palms and seven olives are in place.

  4. Sep 25 · Week 3

    Mainline pressure tested

    The irrigation mainline passed its pressure test before backfill.

Key dates

Work started
Sep 7
This week
Week 9, Nov 2
Final walk-through
Week of Jan 11
Scheduled completion
Jan 22